UPDATES:
  • July 22, 2024 Added videos - 1) May 9, 2023 Regular Planning and Zoning Meeting, 2) August 23, 2023 BoT Special Public Hearing Meeting
  • July 22, 2024 Added Litigation section at end
  • July 24, 2024 Added Journal Article on District Court Ruling
  • July 25, 2024 Added actual signed Ordinance 265 Amending VC Zone Code (January 2018) 
  •  August 20, 2024 Added Judge Lujan Court Order in injunction cases (CV-2024-00118)
  • October 23, 2024 SETTLEMENT REACHED (FOLR-Village-Palindrome-Nangeroni) - Link https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/67198d13ca44790a9616a29a/1729727763219/VLR_FOLR_Palindrome+-+REV+w+Highlight.pdf

 

Village Center StoryBoard


TIMELINE

DOCUMENTATION

2002 The Village created the Village Center Zone to allow for a development pattern that included increased density, new housing options, economic vibrancy, and diversity. 


The VC Zone Code was adopted in 2003


2010 Master Plan for the Village of Los Ranchos (adopted January 19, 2000)


2007 The Village outlined the Village Center Zone Project Area.  


The Board of Trustees declared the area a Metropolitan Redevelopment Area (MRA) due to its under performing commercial activity, deteriorated buildings and large areas of vacant land


The Village actively acquired property in the zone over the succeeding 10 years  


2007 (February) 4th & Osuna Village Center Conditions Analysis & Designation Report



Link:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63ebf25a9c44925eba614166/1676407388845/Fourth+%26+Osuna+Village+Center+Conditions+Analysis+and+Designation+Report+February+2007.pdf 



2018 (January) § 9.2.14 VC – Village Center Zone Code  



Ordinance 265 Amending 2013 Codified Ordinances Chapter 9 Land Use Regulations, Article, Zoning and Zone Map, Section 14, VC - Village Center Zone, § 9.2.14



Link to Zone Code:

https://codelibrary.amlegal.com/codes/losranchosnm/latest/losranchos_nm/0-0-0-3067 


Link to Actual Ordinance - Prior version deleted, new version approved, adopted by Governing Body and signed by Mayor Abraham, January 10, 2018

https://img1.wsimg.com/blobby/go/c6ad2e99-f7e7-45a7-a57f-21ccd5de1669/Village%20Center%20Zone%20Code%202018%20signed.pdf



2018 The Village adopted the Village Center Project MRA Plan (Resolution No. 2018-3-2) on March 14, 2018


The MRA Plan allowed for a public private partnership to develop the project. The New Mexico Metropolitan Redevelopment Code grants powers to the Village to promote developments within blighted areas and authorized the Village to rehabilitate and redevelop the area for public health, safety, and welfare.




2018 (March) Village Center Project MRA Plan 


Link:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63ebee899bb8451539c0974e/1676406414257/Village+Center+Project+MRA+with+MAPs+Final%5B1%5D.pdf 






2018 (April) The Village issued a Request for Proposals (RFP) to identify and select an experienced developer with the adequate finances to acquire, consolidate, design, develop, operate, and eventually own the Village Center site 


2018 (July) Winning Proposal - Palindrome Communities



Link:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63ebebe7d1763b439b83cf88/1676405755364/RFP+Response-FINAL.pdf 



2018 (November) The Village agreed to an MOU with Palindrome Communities LLC


The MOU designated Palindrome as the Village Center developer, summarized understandings, expectations, and intent as a framework for negotiating a binding development agreement to establish the terms for the acquisition, financing, and development of the Property 



2018 (November) Memorandum of Understanding with Palindrome Communities LLC 


Link:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63ebeb6f8fbd833dd0bed11e/1676405615548/1.MOU+VLR+and+Palindrome.pdf 


2020 (October) The Village approved the Purchase, Sale and Development Agreement with Palindrome with Development Timeline



October 14 - 2020 Board of Trustees Regular Meeting




Watch BoT deliberation (30 minutes):

https://www.youtube.com/watch?v=GYLu4bQ596c&t=5595s 


Link to Purchase, Sale and Development Agreement:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/62f6bd091ea0c37a35f7831e/1660337418402/Agreement+w+Timeline.pdf 





2021 (April) Village Center Project Requirements



2021 (April) Village Center Project Requirements - Signed by both parties July 2021


Link:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63f3f2370dfbbb6b81a1a5fe/1676931639848/VC+Project+Requirements+4-21-2021+Signed.pdf 


2021 (April) Presentation to Board of Trustees on Progress




April 14 - 2021 Board of Trustees Regular Meeting




Watch presentation to BoT (27 minutes):

https://www.youtube.com/watch?v=3KbjyzQrlHI&t=3485s 


Link to presentation:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63ebfae4cedf5746c9c1547e/1676409576104/Presentation+Palidrome+BOT+April+2021.pdf 


2021 (October) Presentation to Board of Trustees on Progress



October 2021 Board of Trustees on Progress 


 



Watch presentation to BoT (30 minutes):

https://www.youtube.com/watch?v=r58tgrUuTiQ&t=2602s  


Link to presentation:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/618b049fd96c4d5d2a846aeb/1636500644350/Board+of+Trustees+Presentation+10-13-2021.pdf 



2022 (May) Sketch Plat Approval


Link to document:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63f54d9c74e1d16c1d972dc5/1677020572294/Sketch+Plat+approval.pdf 


2022 (July) Preliminary Plat Approval 


Link to document:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63f54e060d7ceb7355d45f71/1677020678420/Preliminary+Plat+-+7-29-22+-+Signed+TJ+AS+Letter+of+Conditional+Approval.pdf 


2022 (August) Final Plat Approval  


Link to document:

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/63f54e10dce0a657baf12cb1/1677020688699/Final+Plat+Approval.pdf 



2022 (August) Draft Site Rendering 



Link to August 2022 Draft Site Rendering (full scale):

https://static1.squarespace.com/static/600f5ed78afa7f5549aac790/t/64df9938d0a071068cd56901/1692375352686/2022035_TACH_SSW_Rendering_09-16-2022.pdf 


2023 (February) Site Plan Approved


2023 (February) Permits granted


2023 (February) Construction started


2023 (May) FOLR appeals Site Plan approval at P&Z. P&Z approved appeal and recommended BoT vacate Site Development Plans 


2023 (July) FOLR written notice to Village alleging OMA violation 


2023 (August) BoT approves Palindrome appeal of P&Z recommendation 


2023 (September) FOLR appeals BoT ruling to District Court


2024 (May) District Court Judge Denise Barela-Shepherd rules in favor of FOLR that 1) Administrator and P&Z Director lacked legal authority to approve plans AND 2) Approvals should have occurred in an open public meeting


2024 (May) Village BoT voted NOT to appeal the ruling and to file for injunctive relief to stop the project


2024 (May) Palindrome filed motion to reconsider to Judge Barela-Shepherd [pending]


2024 (June) Village filed for injunctive relief to stop the project to District Court

[DENIED - July 23, 2024 - see article below]



May 9, 2023 Regular Planning and Zoning Meeting



Watch FOLR appeal at P&Z (Approximately 3 hours): 
https://www.youtube.com/live/hsZ4cYbtOHs?si=QoOs7xrgmYHJDvq6&t=1116

August 23, 2023 BoT Special Public Hearing Meeting
 

Watch BoT hearing 
https://www.youtube.com/live/Zg86bENvuY4?si=_p7z1kvnklmT7naA&t=6

Link to Judge Denise Barela-Shepherd’s ruling with background, timeline and findings:

https://static1.squarespace.com/static/62b4c68459c1534749f1ceff/t/66350025503b8d77637fba77/1714749477880/FOLRvVillage.pdf 



LITIGATION - Under Development 

January 3, 2024 Palindrome filed Petition for Injunction against Craig and Kueffer seeking to disqualify them from voting in BoT matters involving Palindrome, citing conflict of interest. (Case Number: D-202-CV-2024-00118 - Palindrome Communities LLC, et al., v. Joe D Craig, et al.)

June 6, 2024 Village filed lawsuit for injunctive relief (CV-2024-4849 App for TRO minus exhibits) 

Link to filing: https://img1.wsimg.com/blobby/go/c6ad2e99-f7e7-45a7-a57f-21ccd5de1669/CV-2024-4849%20App%20for%20TRO%20minus%20exhibits.pdf  


** The two cases were consolidated and both are pending before Judge Elaine P. Lujan. Next hearing date  - Tuesday July 23rd at 9 AM **

District judge rules in favor of developer in two issues related to controversial Palindrome Project
Ollie Reed, Albuquerque Journal, N.M.
Tue, July 23, 2024 at 9:01 PM MDT

Court Order filed 8/16/24 in the injunction cases (CV-2024-00118) that were decided by Judge Lujan on July 23, 2024.

______________________


Three other FOLR lawsuits:

1. 9/14/22 FOLR sued Village; Palindrome intervened. Complaint "to Remedy Violations of Due Process of Law." Set for Bench Trial (non-jury) on 11/18/24


2. 3/24/23 FOLR and others filed Complaint against Village and officers and staff "to Remedy Violations of Due Process of Law"


3. 6/11/23 FOLR members Nancy Nangeroni and Joe Craig filed Complaint against Village, BOT, Don Lopez and Palindrome "for Violation of Open Meetings Act." Consolidated into #2.